On 08/27/2010 11:39 AM, Marnie McCormack wrote:
> All,
>
> I'd like to propose a timeline for the next Qpid release - with a target of
> end October.
>
> IIRC, we usually take trunk as stable/defect fixing only for 2 weeks before
> release so that would take us back to 18th Oct for the start of that period.
>
>
> The work I'm closest to, 0-10 implementation on the Java broker, looks like
> it'll be in shape for a release around then. We currently have 186
> Unresolved JIRAs in 0.7, with 34 RfR. What's the feeling - could we aim for
> these dates ?
>
> If so, it'd be good to start updating those JIRAs that might not really be
> unresolved (optmistic ?) and reducing scope down for any that won't
> realistically be completed in time for a release in ~8 weeks.
>
> Thanks&  Regards,
> Marnie
>
>    
I'm +1 on this as well.