Hi Ricardo,

yes you are completely right!
WorkEffortFixedAssetStd should be used to specify the standard machines 
associated to a routing task.
WorkEffortFixedAssetAssign should record the actual machines assigned to 
a production run task.
In general, this is the pattern we are using for this kind of things.

Jacopo


Ricardo Chavez wrote:
> Hello everybody
> I have recently found these two entities, WorkEffortFixedAssetAssign and
> WorkEffortFixedAssetStd, and was wondering if anyone had some 
> information on
> them, such as their purpose and how are they meant to be used, because they
> might be what I'm looking for to implement the feature I described. So, any
> thoughts?
> Thanks in advance.
> Regards,
> 
> -- Ricardo Chavez
> 
> On 9/29/06, Ricardo Chavez <ricardo.jefe@gmail.com> wrote:
>>
>> Hi Jacopo
>>
>> Thanks for the reply. Posting the JIRA feature request right now...
>>
>> -- Ricardo Chavez
>>
>> On 9/28/06, Jacopo Cappellato < tiz@sastau.it> wrote:
>> >
>> > Hi Ricardo,
>> >
>> > there are no plans (that I'm aware of) of implementing this feature so
>> > please post a Jira feature request because others could be 
>> interested in
>> > helping you with this.
>> >
>> > This could be implemented in different ways:
>> >
>> > a) expanding the concept of FixedAsset groups (so that the data model
>> > will
>> > be left mostly unchanged); you create a fixed asset of type group (e.g.
>> > "sewing machines of room A") and this fixed asset is associated to the
>> > task; then you link each sewing machine (other fixed assets) to the
>> > fixed
>> > asset group
>> >
>> > b) (more complex) add new association entities to link a task
>> > (WorkEffort)
>> > to one or more machines (FixedAsset).
>> >
>> > If possible I'd follow the a) path... but I don't know what your
>> > requirements are so this is just a 1 cent opinion.
>> >
>> > Jacopo
>> >
>> > Ricardo Chavez wrote:
>> > > Hello everybody. I have this doubt about production run tasks and
>> > machines.
>> > > Is there a way to associate more than one machine (fixed asset) to a
>> > single
>> > > production run task? That would cover the case when you have many
>> > machines
>> > > working on the same production task, which I think is quite common in
>> > any
>> > > manufacturing business (e.g. many sewing machines working to complete
>> > a
>> > > production run of 1000 T-shirts).
>> > > If this cannot be done yet, are there any plans to implement it? I 
>> can
>> > post
>> > > a JIRA feature request for this (unless, of course, you think it's 
>> not
>> > a
>> > > necessary feature and it needs not to be implemented)
>> > > Thanks in advance for your answer.
>> > > Regards,
>> > >
>> > > -- Ricardo Chavez
>> > >
>> >
>> >
>> >
>>
> 


Mime
View raw message