21.7.-25.7. Work on the code generation, Maven plugin
26.7.-1.8. MyFaces-Core Config and MyFaces Component Lib plugins
2.8.-9.8. MyFaces Extension and Codi plugins
9.8.-15.8. According to the GSoC timeline: Scrub code, write tests,
improve documentation, etc.