Yes, boolean is enough.

In PR example, iteration 30 is just a arbitrary number. I had just
copy and paste Pregel example. Actually, program should run until
convergence is achieved. If you are saying about unit test of
PageRank, then +1.

On Wed, Apr 18, 2012 at 4:22 PM, Praveen Sripati
<praveensripati@gmail.com> wrote:
> 1) I was looking in the ShortestPath#bsp() (1) on when the program gets out
> the main while loop. Not sure if I understood it properly, but it looks a
> bit complicated without much comments. Similar logic has been applied in
> the org.apache.hama.graph.GraphJobRunner#bsp() also.
>
> Basically, each of the bsp task should send a boolean to a master depending
> on any messages have been sent to other peers or not. The master if there
> is atleast one true from any one of the peer, will send a true back to all
> the peers to continue the processing. Or else the bsp task can send a
> boolean to all the peers instead of the master to avoid an additional
> sync(). It is as simple as that.
>
> The number of updates vertex which have been updated should not matter.
> What is the purpose of the updatesMade and the globalUpdateCounts integer
> variables?
>
> 2) Also, in the PageRank(2) the convergence is not tested, the program just
> goes through the loop maxIteration # of times. Is a test for convergence
> required in the graph package?
>
> Praveen
>
> (1) -
> https://svn.apache.org/repos/asf/incubator/hama/branches/0.4/examples/src/main/java/org/apache/hama/examples/ShortestPaths.java
> (2) -
> https://svn.apache.org/repos/asf/incubator/hama/trunk/examples/src/main/java/org/apache/hama/examples/PageRank.java



-- 
Best Regards, Edward J. Yoon
@eddieyoon

Mime
View raw message