Hi Reto,
this plan sounds reasonable to me: +1.
Tommaso

2011/1/2 Reto Bachmann-Gmuer <reto.bachmann@trialox.org>

> Would the following be a realistic timetable?
>
> - Identifying releasable modules: i.e. a set of module sufficient to
> reasonably run clerezza of which all dependencies are available in maven
> central
> - Code freeze on January 23rd: from this moment we do the discussed
> renaming
> of the modules and other cosmetic changes to the code
> - Vote for release starting on the 27th
> - Release February 1st
>
> Cheers,
> Reto
>