From "Alexey Goncharuk (JIRA)" <j...@apache.org>
Subject [jira] [Created] (IGNITE-5552) ServiceProcessor recalculates all service assignments even if there is a pending topology change
Date Tue, 20 Jun 2017 09:36:00 GMT
Alexey Goncharuk created IGNITE-5552:
----------------------------------------

             Summary: ServiceProcessor recalculates all service assignments even if there
is a pending topology change
                 Key: IGNITE-5552
                 URL: https://issues.apache.org/jira/browse/IGNITE-5552
             Project: Ignite
          Issue Type: Improvement
          Components: managed services
    Affects Versions: 1.7
            Reporter: Alexey Goncharuk
             Fix For: 2.2


This behavior was observed in a real cluster of hundreds of nodes and hundreds of services.

After a ~30 new nodes startup, we expected node singletons to be deployed immediately, but
the services were deployed with ~4hr delay on last nodes. The reason for this is the fact
that ALL service deployments are recalculated on ALL discovery events. In this case, a single
discovery event was processed in a time span of 2-5 minutes, which with the lateAffinityAssignment=true
yielded a 4hr delay for the last node.

The quick change that may improve things a lot is aborting current assignment calculations
if there is a pending discovery event needs to be processed.

The rest of the optimizations are put to https://issues.apache.org/jira/browse/IGNITE-5551



--