On Sat, Jun 5, 2010 at 12:46 PM, Jonathan Gray <jgray@facebook.com> wrote:

> The dates sound good, at least on master side of things.
>
> I've got a bunch of half-done stuff on the compaction/flush/split side of
> things that I've been holding off on until the master stuff pushes through.
>  I suspect 6/22 is enough time to finish my stuff, but I may not have all
> patches up by 6/15.  I'll keep that as the target and see how far I can get.
>  I'd really like to at least get the refactor and HBASE-2375 in before the
> dev release, some of the other changes can wait.
>
>
Great. Any chance you could push those works-in-progress off to github? We
could get some more eyes on it early that way, so review will go faster when
it's ready to go?

-Todd


> Also, +1 on doing a dev release of the hadoop branch to ship the dev
> release with.  Part of the way we can get it tested is by putting it out
> there to the community.
>
> JG
>
> > -----Original Message-----
> > From: Todd Lipcon [mailto:todd@cloudera.com]
> > Sent: Thursday, June 03, 2010 10:02 PM
> > To: dev
> > Subject: Working towards a dev release
> >
> > Hey everyone,
> >
> > I'd like to start planning towards a development release this month.
> > Here's
> > my thinking on timeline, working backwards:
> >
> > *Tues, 6/29 - Hadoop Summit, official first release of dev series*
> >
> > It would be great to have a release at this point that we think is
> > moderately usable (ie not significantly less stable than 0.20.n has
> > been).
> > Perhaps some of the new features (eg replication, coprocessors, etc)
> > would
> > still be in progress but I think it would be great to be able to talk
> > up a
> > working installable-today release at the summit.
> >
> > Thinking backwards, from here:
> >
> > *Tues, 6/22 - Major patches committed, first "usable" builds w/ new
> > features
> > *
> >
> > If all the real development features were committed by 6/22, that would
> > give
> > us a week to bang on it suss out the bugs. Those of you working on
> > larger
> > things (eg master fixup), do you think you'll be ready for it to be
> > committed at this point?
> >
> > *Tues, 6/15 - Major patches in review*
> > *
> > *
> > Given the scope of some of the changes in the works (particularly
> > thinking
> > about master work being done at FB right now) I think it would be
> > excellent
> > if the rest of us could start looking at patches by 6/15. Fine if there
> > are
> > still known bugs, but this will give us some days to look at the patch
> > and
> > work in parallel on fixing them.
> >
> > Do these target dates seem reasonable to everyone?
> >