harmony-dev mailing list archives

Site index · List index
Message view « Date » · « Thread »
Top « Date » · « Thread »
From Mark Hindess <mark.hind...@googlemail.com>
Subject Re: [milestone] Proposed next milestone plans
Date Wed, 18 Aug 2010 20:07:22 GMT

In message <4C6BA84A.3010306@gmail.com>, Tim Ellison writes:
>
> We've had lots of good fixes and improvements in the codebase over the
> last few months, so time to take stock with another of our regular
> milestones.
> 
> I would like to propose the following schedule for 5.0M15 & 6.0M3.
> 
>   Feature freeze  Fri 20th August
>   Code freeze     Fri 27th August
>   Publish         Fri 3rd September

+1
 
> If there are any objections or problems with these dates please say.
> As usual, we will track issues that must be fixed for these releases
> using the JIRA "Fix for" field.  To see the list visit the Harmony JIRA
> homepage at:
> 
>   http://issues.apache.org/jira/browse/HARMONY
> 
> and click the "Road Map" link.

This seems like a good candidate for an s.apache.org url so I've set up:

   http://s.apache.org/harmony/roadmap

Regards,
-Mark



Mime