Maybe we can schedule the Java6 branch one week or one month later
than Java5's milestone.
So we can merge the milestone to as part of Java6's updates.


Best Regards
Sean, Xiao Xia Qiu




2009/8/11 Mark Hindess <mark.hindess@googlemail.com>:
>
> We are due another milestone build at the end of the month.  I think we
> should consider the following dates:
>
>  Feature freeze  Fri 14th August
>  Code freeze     Fri 21st August
>  Publish         Fri 28th August
>
> We should track issues that must be fixed for M11 with JIRA using the
> "Fix for" field.  There are currently a few issues marked this way but
> I don't think any of them are "must fix" issues.  To see what they are
> visit the Harmony JIRA homepage at:
>
>  http://issues.apache.org/jira/browse/HARMONY
>
> and click on "5.0M11" entry in the Versions column.
>
> How do people feel about doing milestone release of the java6 branch in
> this timescale?
>
> Regards,