Subject Re: [general] Milestone 10 - Code Freeze
Date Fri, 22 May 2009 10:31:48 GMT
And a follow up reminder - we are now in code freeze and testing period, 
aiming to publish M10 on Friday 29th May.

As usual, defining a bug as "must-fix" in this milestone requires (at 
least) two committers agreement. Please raise test failures on the list 
and open JIRAs where appropriate.

Regards,
Oliver

Tim Ellison wrote:
> Just a reminder.  We are entering feature freeze now, and there is just
> one week left to go to our code freeze date.
>
> No major new functionality gets dropped in from now until after M10.
> Point bug fixes are still ok, and if you have time to do some testing
> and fixing ahead of the test phase all the better.
>
> Feature freeze	Fri 15th May
> Code freeze	Fri 22nd May
> Publish		Fri 29th May
>
> With the 'customary' definitions of what they mean.
>
> Issues that *must* be fixed for M10 are tracked in JIRA using the 'Fix
> for' field.  From the Harmony JIRA homepage [1] click on the "5.0M10"
> package listed in the Versions column to see those targeted for M10.
>
> [1] http://issues.apache.org/jira/browse/HARMONY
>
> Regards,
> Tim
>
>
>   

-- 
Oliver Deakin
Unless stated otherwise above:
IBM United Kingdom Limited - Registered in England and Wales with number 741598. 
Registered office: PO Box 41, North Harbour, Portsmouth, Hampshire PO6 3AU


Mime
View raw message