+1

-Stepan.

On 11/25/07, Tim Ellison <t.p.ellison@gmail.com> wrote:
> So if we agree on producing M4 on Fri Dec 14th, then working back from
> that date we have:
>
> Code freeze on Fri Dec 7th.  Feature freeze on Fri Nov 30th .
>
> So this coming week is the last chance to consider any new features or
> major areas of functionality for inclusion in this milestone.
>
> After Fri 30 Nov our focus is on bug fixing, testing, and stabilizing
> the code ready for the milestone.
>
> After Fri Dec 7th the code is frozen, meaning we are all testing and
> discussing must-fix bugs that have a serious impact on declaring the
> milestone.  Defining a bug as "must-fix" requires (at least) two
> committers during the freeze period (of course, everyone's opinion is
> encouraged).  We aim that this period is no more than a week, but we
> will move the date if necessary to achieve the required quality.
>
> i.e., business as usual <g>
>
> Regards,
> Tim
>
> Spark Shen wrote:
> > Agree.
> >
> > 2007/11/23, Tim Ellison <t.p.ellison@gmail.com>:
> >> I think we should agree a date to release our fourth stable milestone
> >> build.  There have been lots of good fixes and enhancements made
> >> throughout the code, and while we have been doing well at maintaining
> >> stability in 'head', I believe that many users wait for a declared
> >> milestone before moving up.
> >>
> >> I propose that we aim for declaring M4 on Friday Dec 14th.  That is
> >> three weeks from today.
> >>
> >> That date gives us some buffer to overrun if we need it before the
> >> holiday period gets into full swing.  Once get near the end of December
> >> and start of January there are many people taking a well-earned break,
> >> and it will be harder to close out a release.
> >>
> >> To get in practice for an official release, I suggest we also try to
> >> complete the full set of rel eng tasks, like release notes, download
> >> signing, and announcements that we haven't been so good at in the past.
> >>
> >> What do you think?
> >> Tim
> >>

Mime