Subject [jira] Commented: (HADOOP-5985) A single slow (but not dead) map TaskTracker impedes MapReduce progress
Date Mon, 08 Jun 2009 17:24:07 GMT

    [ https://issues.apache.org/jira/browse/HADOOP-5985?page=com.atlassian.jira.plugin.system.issuetabpanels:comment-tabpanel&focusedCommentId=12717332#action_12717332
] 

Aaron Kimball commented on HADOOP-5985:
---------------------------------------

Hong,

This changes the semantics of speculative execution, as I understand it.

Speculative execution does not strictly guarantee that all mappers will emit the same output
for the same input, but it does guarantee that they are all equally "good." So map(A) might
return X, but a second speculative execution of map(A) might return Y. Either X or Y will
finish first and the JT will use exactly one of these.

Your proposal is that some of the reducers can grab their output shard from the X results,
and other reducers can grab their output shard from the Y results.

If we're willing to tell developers about that new contract and make it an option, then wouldn't
be universally applicable. So I still think we'd still need a fallback mechanism like I proposed
here.

> A single slow (but not dead) map TaskTracker impedes MapReduce progress
> -----------------------------------------------------------------------
>
>                 Key: HADOOP-5985
>                 URL: https://issues.apache.org/jira/browse/HADOOP-5985
>             Project: Hadoop Core
>          Issue Type: Bug
>    Affects Versions: 0.18.3
>            Reporter: Aaron Kimball
>
> We see cases where there may be a large number of mapper nodes running many tasks (e.g.,
a thousand). The reducers will pull 980 of the map task intermediate files down, but will
be unable to retrieve the final intermediate shards from the last node. The TaskTracker on
that node returns data to reducers either slowly or not at all, but its heartbeat messages
make it back to the JobTracker -- so the JobTracker doesn't mark the tasks as failed. Manually
stopping the offending TaskTracker works to migrate the tasks to other nodes, where the shuffling
process finishes very quickly. Left on its own, it can take hours to unjam itself otherwise.
> We need a mechanism for reducers to provide feedback to the JobTracker that one of the
mapper nodes should be regarded as lost.

-- 