Subject Re: 1.0.1 release date?
Date Sun, 08 Jan 2006 21:46:50 GMT
I think we could have done a better job in releasing 1.0 by allowing a week for 
testing, a week for incorporation of feedback and follow this process a couple 
of times.  Unfortunately we ended up doing that anyway which cost us about 4 
weeks and the holiday didn't help.  Based on that experience I think the cut off 
  and a named RC release, TCK and bug feedback, cut and put out for another week 
and publish if no major gotchas which I think extends your time frame for about 
two weeks at the end.  Anything short of that I think were trading quality off 
for speediness.

John Sisson wrote:
> Correction to earlier mail.. should be 1st week of Feb.
> 
> John Sisson wrote:
> 
>> How does everyone feel about a changes cutoff for 1.0.1 on Fri 27th 
>> Jan, aiming for a 1.0.1 release in the 1st week of Feb.
>> The 27th would give us three weeks to get bug fixes in and tested.  
>> Considering 1.0.1 is a maintenance release, hopefully it will be 
>> easier to get out the door than 1.0.
>>
>> The only non-bug fix that I am aware of that should be in 1.0.1 is the 
>> IzPack installer.
>>
>> Regards,
>>
>> John
>>
> 
> 
> 
> 