From Bruce Schuchardt <bschucha...@pivotal.io>
Subject Re: Time to starting thinking about cutting the 1.11 release branch?
Date Mon, 21 Oct 2019 19:22:24 GMT
Yes, 11/4 should work okay for this job.  10/25 is too soon.

On 10/21/19 12:18 PM, Alexander Murmann wrote:
> Bruce, that sounds like some great work to get in.
>
> Given this is a discussion about getting our release cut and shipped on our
> quarterly release train. How does this fit in with the two proposed dates
> of cutting 11/4 or 10/25? Are you suggesting to keep 11/4 as Owen original
> proposed?
>
> On Mon, Oct 21, 2019 at 12:08 PM Bruce Schuchardt <bschuchardt@pivotal.io>
> wrote:
>
>> I have some backward compatibility work in membership that I want to
>> complete for 1.11.  Doing so will remove the need to keep a bunch of
>> other backward-compatibility code around and simplify things in the
>> membership packages.
>>
>> On 10/18/19 5:08 PM, Owen Nichols wrote:
>>> Knowing on what day the release will get cut allows community members to
>> plan their contributions. --geode wiki <
>> https://cwiki.apache.org/confluence/display/GEODE/Release+Schedule>
>>> Oct 25 sounds like a good date to plan around!
>>>
>>> As much as I would love to volunteer again, this would be a really
>> fantastic opportunity for a new committer who hasn’t done a release
>> before.  Don’t be shy!  No prior experience required!
>>> -Owen
>>>
>>>> On Oct 18, 2019, at 2:47 PM, Alexander Murmann <amurmann@apache.org>
>> wrote:
>>>> Hi Owen,
>>>>
>>>> Thanks for bringing this up!
>>>>
>>>> Given our track record, instability we have seen in the pipeline
>> recently
>>>> and that the holidays are coming up, I wonder if it makes sense to give
>> the
>>>> release more time to stabilize and cut the branch even earlier. Maybe we
>>>> could try to find a release manager early next week and cut it Oct 25th?
>>>>
>>>> Thoughts?
>>>>
>>>> On Fri, Oct 18, 2019 at 12:25 PM Owen Nichols <onichols@pivotal.io>
>> wrote:
>>>>> Geode's stated policy <
>>>>>
>> http://apache.org/foundation/records/minutes/2018/board_minutes_2018_11_21.txt
>>>>> is to cut quarterly release branches on a time-based schedule
>>>>> (specifically, the Monday on or after Feb 1, May 1, Aug 1, Nov 1).
>>>>>
>>>>> Here’s a potential timeline:
>>>>>
>>>>> Now
>>>>> [Contributors] Start thinking about how to make features already in
>>>>> develop as stable as possible.
>>>>> [Contributors] Hold off on merging new potentially-destabilizing work
>>>>> until after the branch is cut.
>>>>> [All] Start a DISCUSS thread if you want to propose changes to release
>>>>> cadence, release process, or the timing of this release specifically.
>>>>>
>>>>> Mon Oct 28
>>>>> Call for someone to volunteer to be the 1.11 Release Manager.  No prior
>>>>> experience needed!  Unforgettable adventure guaranteed!
>>>>> Release manager begins working through
>>>>>
>> https://cwiki.apache.org/confluence/display/GEODE/Releasing+Apache+Geode
>>>>> Mon Nov 4
>>>>> Cut release/1.10.0 branch (only critical fixes accepted from this point
>>>>> forward)
>>>>>
>>>>> Thu Nov 21 (estimate; actual date depends how many critical fixes must
>> be
>>>>> brought in to stabilize the release branch)
>>>>> 1.11.0.RC1
>>>>>
>>>>> Thu Dec 5 (estimate; actual date depends how many RC's it takes)
>>>>> Officially release 1.11.0