From Jacques Nadeau <jacq...@dremio.com>
Subject Re: Time for a 1.5 release?
Date Mon, 25 Jan 2016 19:20:05 GMT
I think the main things are 4196 and 4291 should be completed. I know Amit
was able to reproduce 4196 locally this weekend so I think we're close on
that.

--
Jacques Nadeau
CTO and Co-Founder, Dremio

On Mon, Jan 25, 2016 at 10:14 AM, Zelaine Fong <zfong@maprtech.com> wrote:

> Any updates on this?  What's blocking us from taking this to a vote -- the
> sort merge join issues?
>
> -- Zelaine
>
> On Tue, Jan 19, 2016 at 4:18 PM, Jacques Nadeau <jacques@dremio.com>
> wrote:
>
> > Bumping this thread...
> >
> > Here are the issues that were mentioned in this thread along with a
> > proposed categorization:
> >
> > Release Blockers
> > In-progress Amit https://issues.apache.org/jira/browse/DRILL-4190
> > In-progress Amit https://issues.apache.org/jira/browse/DRILL-4196
> > Ready to merge Jacques https://issues.apache.org/jira/browse/DRILL-4246
> > In-review Jinfeng https://issues.apache.org/jira/browse/DRILL-4256
> > In-progress Jacques https://issues.apache.org/jira/browse/DRILL-4278
> > Ready to merge Laurent https://issues.apache.org/jira/browse/DRILL-4285
> > Nice to Have
> > Open Jason/Hakim https://issues.apache.org/jira/browse/DRILL-4247
> > In-progress Jason https://issues.apache.org/jira/browse/DRILL-4203
> > Open Jacques https://issues.apache.org/jira/browse/DRILL-4266
> > Ready to merge Jacques https://issues.apache.org/jira/browse/DRILL-4131
> >
> > What do others think? Let's try to get the blockers wrapped up in the
> next
> > day or two and start a release vote...
> >
> >
> >
> > --
> > Jacques Nadeau
> > CTO and Co-Founder, Dremio
> >
> > On Mon, Jan 4, 2016 at 1:48 PM, Jason Altekruse <
> altekrusejason@gmail.com>
> > wrote:
> >
> > > Hello All,
> > >
> > > With the allocator changes merged and about a month since the last
> > release
> > > I think it would be good to start a vote soon. I would like to
> volunteer
> > to
> > > be release manager.
> > >
> > > I know that there were some issues that were identified after the
> > transfer
> > > patch was merged. I think that these issues should be fixed before we
> > cut a
> > > release candidate.
> > >
> > > From looking at the associated JIRAs it looked like there was a
> possible
> > > short term fix just adjusting the max_query_memory_per_node option, and
> > > some more involved work to change how we determine the correct time to
> > > spill during external sort. I believe it makes sense to make external
> > sort
> > > work well with the newly improved memory accounting before cutting a
> > > release, but I'm not sure how much work is left to be done there. [1]
> > >
> > > Please respond with your thoughts on a release soon and any JIRAs you
> > would
> > > like to include in the release.
> > >
> > > [1] - https://issues.apache.org/jira/browse/DRILL-4243
> > >
> > > Thanks,
> > > Jason
> > >
> >
>