From Rick Hillegas <Richard.Hille...@Sun.COM>
Subject Re: Wrapping up coding for 10.2
Date Tue, 27 Jun 2006 19:13:00 GMT
Thanks, Mike. Here's a potential schedule of release candidates. Is this 
unorthodox or too aggressive? Could you propose a more realistic schedule?

August 10 : Create branch and generate snapshot for testing

August 24 : Generate first release candidate

August 31 - September 7 : Generate second release candidate

September 15 : If necessary generate third release candidate with 
hopefully quick vetting

Regards,
-Rick

Mike Matrigali wrote:

> august 10th seems fine for me.  Your schedule does not talk in terms of
> release candidates.  I am ok with a code complete on august 10th and
> assuming a rc1 is created on august 10th it seems pretty aggressive to
> have all testing and all fixes from that testing in a final rc 2 weeks
> later.  It seems like we needed more time than that for a point release
> from a stable branch, seems likely that this new branch will take longer.
>
> Rick Hillegas wrote:
>
>> I hate to be a nudge, but I didn't get a response when I asked this 
>> question last week: Do we expect to be done with development for 10.2 
>> by August 10?
>>
>> I expect that the JDBC4 work will have wrapped up by then. Besides 
>> the JDBC4 effort, 10.2 is waiting for feature work from Army, Dan, 
>> and Satheesh. Do you guys think you'll be done by August 10?
>>
>> If anyone else is working on 10.2 features, could you let us know 
>> whether August 10 sounds like a reasonable date for cutting a release 
>> branch?
>>
>> Thanks,
>> -Rick
>>
>>
>