august 10th seems fine for me.  Your schedule does not talk in terms of
release candidates.  I am ok with a code complete on august 10th and
assuming a rc1 is created on august 10th it seems pretty aggressive to
have all testing and all fixes from that testing in a final rc 2 weeks
later.  It seems like we needed more time than that for a point release
from a stable branch, seems likely that this new branch will take longer.

Rick Hillegas wrote:
> I hate to be a nudge, but I didn't get a response when I asked this 
> question last week: Do we expect to be done with development for 10.2 by 
> August 10?
> 
> I expect that the JDBC4 work will have wrapped up by then. Besides the 
> JDBC4 effort, 10.2 is waiting for feature work from Army, Dan, and 
> Satheesh. Do you guys think you'll be done by August 10?
> 
> If anyone else is working on 10.2 features, could you let us know 
> whether August 10 sounds like a reasonable date for cutting a release 
> branch?
> 
> Thanks,
> -Rick
> 
> 