Yes, you should run them on the same schedule and let Continuum  
resolve the dependencies between them.

- Brett

On 20/10/2008, at 6:03 AM, maria@funambol.com wrote:

> Hi,
> I have a techincal question
> is it ok to schedule two projects belonging to the same group and  
> dependencies between them in the same hour?
> because I see that continuum resolves dependencies between the two  
> projects,  if carried out by console,
> is this true even when they are scheduled?
>
> for example I have two projects A and B, with A dependent on B,
> can you schedule these at the same time?
> or should I say a continuum schedule A before B?
>
>
> thank you very much
> Maria
>

--