Just an idea, but maybe every schedule should have its own working
directory (or at least an option should be present to configure it that 
way),
this way the code changes for one schedule wouldn't consumed by the other
schedule. Wiping out when "building fresh" means that snapshot artifacts
get generated that can be exactly the same from build to build...

I understand this might mean pretty drastic changes to the data model 
though.

-Olivier

Jesse McConnell wrote:
> set the one that is to build at midnight to 'build fresh'
>
> that will blow away the working copy and check it out again and build it
>
> jesse
>
> On 6/28/07, Martin Alejandro Villalobos 
> <martin.villalobos@globant.com> wrote:
>> Hello, I've a question.
>> I want add two diferentes schedules to a project in continuum, actually
>> is using 1.1-alpha-2.
>> I want that one schedule that throw each five minutes and the second
>> schedule will be throw one time at midnight.
>> The problem es that, when the last build is generated before the
>> midnight is done, then the next update will not see changes from the
>> previous.
>> There is some solution for this scenario?
>>
>> Thanks for all.
>>
>> Martin.
>>
>>
>
>