Hi all,

I’d like to propose that we shift all future releases forward by roughly 2 month. So, the
releases would be as following (note that 5.2.0 is on the “legacy” schedule):


	5.2.0 — December 2014
	5.3.0 — April 2015 (this is an LTS)
	6.0.0 — July 2015
	6.1.0 — October 2015
	6.2.0 — January 2016
	6.3.0 — April 2016  (this is an LTS)


The rationale for this is basically that a release in November almost never makes sense. No
one will deploy anything around Thanksgiving and/or the winter holidays. In addition, I feel
these schedule fits better into how we have been scheduling ATS Summits.

Thoughts?

— Leif