Billow Gao created CASSANDRA-6225:
-------------------------------------

             Summary: GCInspector should not wait after ConcurrentMarkSweep GC to flush memtables
and reduce cache size
                 Key: CASSANDRA-6225
                 URL: https://issues.apache.org/jira/browse/CASSANDRA-6225
             Project: Cassandra
          Issue Type: Bug
          Components: Core
         Environment: Cassandra 1.2.9, Cassandra 1.2.10
            Reporter: Billow Gao


In GCInspector.logGCResults, cassandra won't flush memtables and reduce Cache Sizes until
there is a ConcurrentMarkSweep GC. It caused a long pause on the service. And other nodes
could mark it as DEAD.

In our stress test, we were using 64 concurrent threads to write data to cassandra. The heap
usage grew up quickly and reach to maximum.
We saw several ConcurrentMarkSweep GCs which only freed very few rams until a memtable flush
was called. The other nodes marked the node as DOWN when GC took more than 20 seconds.
{code}
INFO [ScheduledTasks:1] 2013-10-18 15:42:36,176 GCInspector.java (line 119) GC for ConcurrentMarkSweep:
27481 ms for 1 collections, 5229917848 used; max is 6358564864
 INFO [ScheduledTasks:1] 2013-10-18 15:43:14,013 GCInspector.java (line 119) GC for ConcurrentMarkSweep:
27729 ms for 1 collections, 5381504752 used; max is 6358564864
 INFO [ScheduledTasks:1] 2013-10-18 15:43:50,565 GCInspector.java (line 119) GC for ConcurrentMarkSweep:
29867 ms for 1 collections, 5479631256 used; max is 6358564864
 INFO [ScheduledTasks:1] 2013-10-18 15:44:23,457 GCInspector.java (line 119) GC for ConcurrentMarkSweep:
28166 ms for 1 collections, 5545752344 used; max is 6358564864
 INFO [ScheduledTasks:1] 2013-10-18 15:44:58,290 GCInspector.java (line 119) GC for ConcurrentMarkSweep:
29377 ms for 2 collections, 5343255456 used; max is 6358564864
{code}
{code}
INFO [GossipTasks:1] 2013-10-18 15:42:29,004 Gossiper.java (line 803) InetAddress /1.2.3.4
is now DOWN
 INFO [GossipTasks:1] 2013-10-18 15:43:06,901 Gossiper.java (line 803) InetAddress /1.2.3.4
is now DOWN
 INFO [GossipTasks:1] 2013-10-18 15:44:18,254 Gossiper.java (line 803) InetAddress /1.2.3.4
is now DOWN
 INFO [GossipTasks:1] 2013-10-18 15:44:48,507 Gossiper.java (line 803) InetAddress /1.2.3.4
is now DOWN
 INFO [GossipTasks:1] 2013-10-18 15:45:32,375 Gossiper.java (line 803) InetAddress /1.2.3.4
is now DOWN
{code}

We found two solutions to fix the long pause which result in a DOWN status.
1. We reduced the maximum ram to 3G. The behavior is the same, but gc was faster(under 20
seconds), so no nodes were marked as DOWN

2. Running a cronjob on the cassandra server which period call nodetool -h localhost flush.

Flush after a full gc just make thing worse and waste time spent on GC. In a heavily load
system, you would have several full GCs before a flush can finish. (a flush may take more
than 30 seconds)

Ideally, GCInspector should has a better logic on when to flush memtable. 
1. Flush memtable/reduce cache size when it reached the threshold(smaller than full gc threshold).
2. prevent frequently flush by remembering the last running time.

If we call flush before a full gc, then the full gc will release those rams occupied by memtable.
Thus reduce the heap usage a lot. Otherwise, full gc will be called again and again until
a flush was finished.





--