Hi

Thanks for your feedback. Really appreciate it.
My responses inline starting with [AS].

Thanks
Anindya


- The task in PENDING state might never get scheduled due to variety of
> reasons, e.g.: unsatisfied constraints, unreasonable resource requirements
> and etc. Furthermore, if the task eventually gets scheduled, it may never
> reach RUNNING or more likely fail repeatedly and get THROTTLED for
> flapping. Neither can be considered a successful update criteria.
>
> - Assuming PENDING tasks are only blocked by the lack of resources and get
> unblocked eventually, having hundreds or thousands of PENDING tasks
> transitioning to RUNNING at the same time may and most likely will result
> in an unpredictable performance problems on the package retrieval (e.g.:
> HDFS) or application side (e.g.: backend connections/load).
>
> [AS]  Agreed on the use case for both of the first 2 points. However,
those scenarios exist anyways for "aurora create" where it actually keeps
the instances that cannot be executed immediately in PENDING state (and
does not terminate them).
When a aurora create is done and if one or more instances are in PENDING
state, those instances may never get scheduled for the reasons you
mentioned in point 1. Furthermore, if a large number of such instances get
scheduled at the same time (in future), you could run into unpredictable
latency/performance issues.

Currently, aurora create is asynchronous whereas aurora update is
synchronous which is leading to an inconsistent behavior of how instances
are scheduled in create vs update. I think providing an additional
mechanism for the behavior of create and update to be consistent would
certainly help address the "unexpected failures" due to PENDING instances
in a aurora update. I think that using rollback=False is undesirable due to
the inconsistent handling based on my earlier example.

Regarding performance/latency concerns, there could be a throttling
mechanism built in based on the # of the instances (or based on some other
policy) that are launched in a given period of time (just a thought). This
problem is not specific to create or update but a generic one that needs to
be addressed separately.

- A mixed update (with updating existing instances and adding new) may
> result in a degraded service state where some or all instances may be
> killed with no replacement coming online (i.e. a new update config has
> resource bump that cannot be satisfied). In the worst case, this may result
> in a complete service outage.
>

[AS] This is indeed a good point. I think that this modification in
behavior should affect only while adding new instances or for existing
instances not in RUNNING state. If update to existing instances in RUNNING
state fail, I think the current implementation of rollback should kick in
since otherwise, it might lead to service degradation or outage.

Essentially, aurora update should ensure any existing instances that are in
RUNNING state should continue to be in RUNNING state. Any failure should
kick in rollback (unless rollback=False) but if a new instance is in
PENDING, or an old instance that was in PENDING is still in PENDING after
the update, we do not consider it to be a failure and terminate the whole
update operation like it is the case today.


> Thanks,
> Maxim
>
>
> On Wed, May 14, 2014 at 11:01 PM, Anindya Sinha <anindya.sinha@gmail.com
> >wrote:
>
> > Hi
> >
> > Wanted to propose a modification in handling of aurora update when the
> job
> > or a task cannot be scheduled immediately based on my understanding of
> job
> > scheduling within aurora.
> > Please feel free to share your comments and/or concerns.
> >
> > Thanks
> > Anindya
> >
> > *Scenario*
> > Assume we have a job with 2 RUNNING instances (say instance 0 and 1) in
> the
> > cluster, and then "aurora update" is issued on the same job key which
> bumps
> > up the instance count to say 5. By default, it keeps instance 0 and 1
> > intact, and attempts to launch 3 additional instances and waits for
> > UpdateConfig.watch_secs for it to be in RUNNING state before moving on
> for
> > each instance.
> >
> > Assume the cluster is in a state where only 1 additional instance can be
> > launched due to resource unavailability. Hence, instance 2 is executed
> (is
> > in RUNNING state) and instance 3 moves to PENDING state and when
> > UpdateConfig.restart_threshold expires, it deems this instance to be a
> > failed instance.
> > If UpdateConfig.rollback_on_failure is True(default), it rolls back the
> > changes done in the update and terminates instances 2 and 3.
> > If UpdateConfig.rollback_on_failure is False, it does NOP keeping
> instances
> > 0 through 2 in RUNNING, and instance 3 in PENDING. Instance 4 is never
> > attempted in either of the scenarios.
> >
> > *Proposal*
> > I propose that in aurora update, we should consider an instance in
> PENDING
> > state after UpdateConfig.restart_threshold timeout NOT to be failed case
> >  (and keep them in PENDING state). The reason behind this is that these
> > instances which could not be scheduled to execute at the time of aurora
> > update can be scheduled eventually in the future once there is a host in
> > the cluster that becomes available to run these instances (based on
> > resource availability in the future).
> >
> > In the current approach, instance 4 is not even attempted to be scheduled
> > since instance 3 is considered to be a failure. Further, the scheduling
> of
> > jobs within aurora update should ideally be treated similar to aurora
> > create (since in case of a aurora create with instance count=5, we would
> > have 3 RUNNING instances and 2 instances in PENDING state assuming the
> > cluster is in a similar state).
> >
> > UpdateConfig.rollback_on_failure=False does not address the above use
> case
> > for all scenarios since:
> > a) It works if the PENDING instance is the last instance to be launched,
> > but fails if there are additional instances to be launched (as in the
> > example above).
> > b) It disables rollback which may not be desirable for "real" failures to
> > launch tasks in the cluster.
> >
> > Here is a JIRA that references this issue (which contains the same
> details
> > as in this email though):
> > Reference: https://issues.apache.org/jira/browse/AURORA-413
> >
>