Srimanth Gunturi commented on AMBARI-6529:
------------------------------------------

+1 for patch.

> UI shows incorrect percentage completion on large cluster
> ---------------------------------------------------------
>
>                 Key: AMBARI-6529
>                 URL: https://issues.apache.org/jira/browse/AMBARI-6529
>             Project: Ambari
>          Issue Type: Bug
>          Components: client
>    Affects Versions: 1.6.1
>            Reporter: Xi Wang
>            Assignee: Xi Wang
>             Fix For: 1.7.0
>
>         Attachments: AMBARI-6529.patch
>
>
> In Background operation window, a request is completed with 100% percentage but the progress
bar is not green.
> Reason:
> The API request object was showing "progress_percent: 99.96754867698452", but UI was
showing 100% with a blue stripe progress bar.
> If anything, UI should round down to the nearest integer, because at 100%, the bar should
be either green or red.



--