From Christopher <ctubb...@apache.org>
Subject Re: [DISCUSS] Updating planned release dates
Date Wed, 26 Feb 2014 00:50:53 GMT
Seems reasonable to update these tentatively in JIRA... but I hope
1.6.0 is out before the end of March.

I would say that the the 1.4.5 release will probably not benefit from
1.5.1's lessons learned much, though. A lot of work went into
simplifying/automating the release process in 1.5.0 that I have no
intention of replicating for 1.4.5. It may be that it would be a
minimal effort to do that, but my guess is that the release processes
between 1.4.5 and 1.5.1 will be very different.

--
Christopher L Tubbs II
http://gravatar.com/ctubbsii


On Mon, Feb 24, 2014 at 7:42 PM, Sean Busbey <busbey+lists@cloudera.com> wrote:
> Right now, Jira lists the following scheduled release dates:
>
> * 1.5.1 : 2013-07-24
> * 1.4.5 : 2013-10-31
> * 1.6.0 : 2013-11-24
>
> I'd like to update these to reflect when we currently think things are
> likely to complete.
>
> Here's my WAG:
>
> * 1.5.1 : 2014-02-28
> * 1.4.5 : 2014-03-19
> * 1.6.0 : 2014-05-29
>
> My reasoning:
>
> * 1.5.1 RC2 failed due to a miscommunication, RC3 is unlikely to have issues
> * AFAIK, 1.4.5 still needs to go through most of the long run tests and
> that will take time. I'd like to wait to start until we have lessons from
> the 1.5.1 release in hand.
> * 1.6.0 still has a ton of tickets, that date is based on a net burn down
> rate of just over 1 per business day (after adjusting for the time it takes
> to do tests)
>
> Thoughts?
>
> -Sean