From Sean Busbey <bus...@cloudera.com>
Subject Re: Schedule for 1.6.0 release?
Date Wed, 18 Sep 2013 15:16:03 GMT
+1 for "Feature Freeze" means only bug fixes happen after the date, which
implies major code additions and changes are already in place with
appropriate tests.

I presume on feature freeze date we'll handle step 1 of the proposed git
workflow for releases (branch to 1.6.0-SNAPSHOT and increment version in
master)?


On Wed, Sep 18, 2013 at 7:49 AM, Eric Newton <eric.newton@gmail.com> wrote:

> I'm ok to leave some documentation tasks for the test period, but all the
> new features should have unit tests, integration tests, and RW tests.
>
>
> On Wed, Sep 18, 2013 at 10:48 AM, Josh Elser <josh.elser@gmail.com> wrote:
>
> > +1 by the end of the year with adequate time for testing.
> >
> > Just so we're all clear (because I don't remember where we ended up
> > either), feature freeze means "all features tagged for 1.6.0 must be
> > finished", right? In other words, if I had something planned for 1.6.0
> that
> > I haven't started, I need to finish it before the feature freeze date
> > regardless of whether or not it's a new feature or not? In other words,
> by
> > "feature freeze" we really mean "only bug-fixes"?
> >
> >
> > On Wed, Sep 18, 2013 at 10:40 AM, Eric Newton <eric.newton@gmail.com>
> > wrote:
> >
> > > +1
> > >
> > > I absolutely need to have multiple volume support in a release by the
> > > end-of-year.
> > >
> > >
> > > On Wed, Sep 18, 2013 at 10:36 AM, Keith Turner <keith@deenlo.com>
> wrote:
> > >
> > > > We do need to get this settled.  What about end of year target for
> > > release
> > > > date and feature freeze date at end of Oct?
> > > >
> > > >
> > > > On Tue, Aug 27, 2013 at 4:26 PM, Mike Drob <mdrob@mdrob.com> wrote:
> > > >
> > > > > I wanted to revive this conversation, since fall is fast
> approaching.
> > > One
> > > > > reasonable target for a release date might be to try and get
> > something
> > > > done
> > > > > before Hadoop World/Strata NY, which is the last week of October.
> > That
> > > > is a
> > > > > bit sooner than initially planned, but would be a great bit of PR
> if
> > it
> > > > > were possible. Regardless, we need to seriously think about a
> feature
> > > > > freeze date and get that agreed upon.
> > > > >
> > > > > Mike
> > > > >
> > > > >
> > > > > On Fri, Jul 12, 2013 at 2:14 PM, Eric Newton <
> eric.newton@gmail.com>
> > > > > wrote:
> > > > >
> > > > > > Absolutely this would be helpful!
> > > > > >
> > > > > > I have access to a 10-node cluster, and regularly run the
> > continuous
> > > > > ingest
> > > > > > test, and the random walk tests for long periods (24-48 hours)
> > prior
> > > to
> > > > > > release.  Running these sooner can shorten the release cycle
> quite
> > a
> > > > bit.
> > > > > >
> > > > > > If anyone has access to a medium-sized cluster (say, 100-500
> nodes)
> > > > that
> > > > > > can be used for scale testing, even if only for a short period,
> or
> > > > shared
> > > > > > with other users, that would be helpful, too.
> > > > > >
> > > > > > -Eric
> > > > > >
> > > > > >
> > > > > >
> > > > > > On Fri, Jul 12, 2013 at 2:06 PM, Donald Miner <
> > > dminer@clearedgeit.com
> > > > > > >wrote:
> > > > > >
> > > > > > > I've talked to a couple of people about this in person,
but
> > figured
> > > > I'd
> > > > > > put
> > > > > > > it out here.
> > > > > > >
> > > > > > > I have access to a 16 node cluster in my lab that we typically
> > use
> > > > for
> > > > > > R&D
> > > > > > > type projects. We have accumulo on it right now and is
> typically
> > > > doing
> > > > > > > something hadoop related. If there is a need to do testing
of
> > > > accumulo
> > > > > > > release on bare metal with respectable equipment, let me
know
> how
> > > we
> > > > > > might
> > > > > > > be able to contribute.
> > > > > > >
> > > > > > > -Don
> > > > > > >
> > > > > > >
> > > > > > > On Thu, Jul 11, 2013 at 5:43 PM, Dave Marion <
> > dlmarion@comcast.net
> > > >
> > > > > > wrote:
> > > > > > >
> > > > > > > > Historically, how long has it taken to complete testing
of
> > > release
> > > > > > > > candidates? Subtract that from 1 November and that
should be
> > the
> > > > > target
> > > > > > > > date. Based on 1.5.0, that means feature complete
is
> tomorrow,
> > > > right?
> > > > > > :-)
> > > > > > > >
> > > > > > > > -----Original Message-----
> > > > > > > > From: Sean Busbey [mailto:busbey@cloudera.com]
> > > > > > > > Sent: Thursday, July 11, 2013 5:17 PM
> > > > > > > > To: dev@accumulo.apache.org
> > > > > > > > Subject: Schedule for 1.6.0 release?
> > > > > > > >
> > > > > > > > One of the action items out of the 1.6.0 discussion[1]
was
> that
> > > > we'd
> > > > > > use
> > > > > > > > the list to decide on a target release date, feature
set, and
> > > > > > incremental
> > > > > > > > milestones for Accumulo 1.6.0.
> > > > > > > >
> > > > > > > > I know the initial plan was to aim for November, and
right
> now
> > > Jira
> > > > > > says
> > > > > > > > as much[2].
> > > > > > > >
> > > > > > > > That's only ~4 months away, so we should lay out some
plans.
> > When
> > > > do
> > > > > we
> > > > > > > > need to target feature complete to meet that goal?
When does
> > code
> > > > > > freeze
> > > > > > > > need to happen?
> > > > > > > >
> > > > > > > >
> > > > > > > >
> > > > > > > > [1]:
> > > > > > > >
> > > > > > > >
> > > > > > >
> > > > > >
> > > > >
> > > >
> > >
> >
> https://docs.google.com/a/cloudera.com/document/d/1FkP2dDE4zzH1ou89_-qpW6-7dtBj9XdMRGjFnnLGrTI/edit
> > > > > > > > [2]:
> > > > > > >
> > > >
> https://issues.apache.org/jira/browse/ACCUMULO/fixforversion/12322468
> > > > > > > >
> > > > > > > > --
> > > > > > > > Sean
> > > > > > > >
> > > > > > > >
> > > > > > >
> > > > > > >
> > > > > > > --
> > > > > > > *
> > > > > > > *Donald Miner
> > > > > > > Chief Technology Officer
> > > > > > > ClearEdge IT Solutions, LLC
> > > > > > > Cell: 443 799 7807
> > > > > > > www.clearedgeit.com
> > > > > > >
> > > > > > > --
> > > > > > >  This communication is the property of ClearEdge IT Solutions,
> > LLC
> > > > and
> > > > > > may
> > > > > > > contain confidential and/or privileged information. Any
review,
> > > > > > > retransmissions, dissemination or other use of or taking
of any
> > > > action
> > > > > in
> > > > > > > reliance upon this information by persons or entities other
> than
> > > the
> > > > > > > intended recipient is prohibited. If you receive this
> > communication
> > > > in
> > > > > > > error, please immediately notify the sender and destroy
all
> > copies
> > > of
> > > > > the
> > > > > > > communication and any attachments.
> > > > > > >
> > > > > >
> > > > >
> > > >
> > >
> >
>



-- 
Sean