Subject Re: Schedule for 1.6.0 release?
Date Fri, 12 Jul 2013 18:14:23 GMT
Absolutely this would be helpful!

I have access to a 10-node cluster, and regularly run the continuous ingest
test, and the random walk tests for long periods (24-48 hours) prior to
release.  Running these sooner can shorten the release cycle quite a bit.

If anyone has access to a medium-sized cluster (say, 100-500 nodes) that
can be used for scale testing, even if only for a short period, or shared
with other users, that would be helpful, too.

-Eric



On Fri, Jul 12, 2013 at 2:06 PM, Donald Miner <dminer@clearedgeit.com>wrote:

> I've talked to a couple of people about this in person, but figured I'd put
> it out here.
>
> I have access to a 16 node cluster in my lab that we typically use for R&D
> type projects. We have accumulo on it right now and is typically doing
> something hadoop related. If there is a need to do testing of accumulo
> release on bare metal with respectable equipment, let me know how we might
> be able to contribute.
>
> -Don
>
>
> On Thu, Jul 11, 2013 at 5:43 PM, Dave Marion <dlmarion@comcast.net> wrote:
>
> > Historically, how long has it taken to complete testing of release
> > candidates? Subtract that from 1 November and that should be the target
> > date. Based on 1.5.0, that means feature complete is tomorrow, right? :-)
> >
> > -----Original Message-----
> > From: Sean Busbey [mailto:busbey@cloudera.com]
> > Sent: Thursday, July 11, 2013 5:17 PM
> > To: dev@accumulo.apache.org
> > Subject: Schedule for 1.6.0 release?
> >
> > One of the action items out of the 1.6.0 discussion[1] was that we'd use
> > the list to decide on a target release date, feature set, and incremental
> > milestones for Accumulo 1.6.0.
> >
> > I know the initial plan was to aim for November, and right now Jira says
> > as much[2].
> >
> > That's only ~4 months away, so we should lay out some plans. When do we
> > need to target feature complete to meet that goal? When does code freeze
> > need to happen?
> >
> >
> >
> > [1]:
> >
> >
> https://docs.google.com/a/cloudera.com/document/d/1FkP2dDE4zzH1ou89_-qpW6-7dtBj9XdMRGjFnnLGrTI/edit
> > [2]:
> https://issues.apache.org/jira/browse/ACCUMULO/fixforversion/12322468
> >
> > --
> > Sean
> >
> >
>
>
> --
> *
> *Donald Miner
> Chief Technology Officer
> ClearEdge IT Solutions, LLC
> Cell: 443 799 7807
> www.clearedgeit.com
>
> --
>  This communication is the property of ClearEdge IT Solutions, LLC and may
> contain confidential and/or privileged information. Any review,
> retransmissions, dissemination or other use of or taking of any action in
> reliance upon this information by persons or entities other than the
> intended recipient is prohibited. If you receive this communication in
> error, please immediately notify the sender and destroy all copies of the
> communication and any attachments.
>

Mime
  • Unnamed multipart/alternative (inline, None, 0 bytes)
View raw message